Portsmouth Gaseous Diffusion Plant
The Portsmouth Gaseous Diffusion Plant is located in south central Ohio, approximately 32 kilometers (20 miles) north of Portsmouth, Ohio, and 112 kilometers (70 miles) south of Columbus, Ohio. The site is situated on a 1,483-hectare (3,708-acre) federal reservation approximately 6.5 kilometers (4 miles) south of the Village of Piketon.
The plant, which employs about 2,000 people, has a fenced area of about 640 acres, 93 of which contain process buildings under roof that include about 2,100 enrichment stages. The plant has a design capacity of 7.4 million SWU per year. The Portsmouth plant enriches product shipped from the Paducah plant to meet customer requirements and manages the delivery of low enriched uranium to customers worldwide.
In August 1952, the AEC selected a tract of land in the Ohio Valley along the Scioto River in Pike County for the site of the Portsmouth Gaseous Diffusion Plant. Site selection was based on the availability of a vast expanse of relatively flat terrain -- the original tract was 4,000 acres -- as well as availability of large amounts of electrical power, a dependable source of water, local labor and suitable transportation routes.
In March 1956, the more than $1.2 billion plant was completed six months ahead of schedule by Peter Kiewett Sons of Nebraska, the construction contractor, at a cost of $750 million, or more than $460 million less than the estimated construction cost. Construction required 69 million man-hours, more than 68,000 drawings and as many as 22,500 construction workers at its peak in the summer of 1954. More than 1,200 acres were cleared and more than 4.5 million cubic yards of earth were moved.
In the 1960s, the Portsmouth plant's mission changed from enriching uranium for nuclear weapons to a more commercial focus. Today, the USEC facilities in Paducah, Kentucky, and Portsmouth, Ohio, work in tandem to enrich uranium for fuel in commercial nuclear power plants. The Paducah Gaseous Diffusion Plant enriches uranium up to 2.75 percent and then ships it to Portsmouth for further enrichment to five percent.

Construction of the Portsmouth Gaseous Diffusion Plant began in late 1952 to expand the Federal Government's gaseous diffusion program already in place at Oak Ridge, Tennessee and Paducah, Kentucky. The facility was built to increase the production of enriched uranium at rates substantially above the other two facilities because highly-enriched uranium was required for use in nuclear submarine reactors, and low-enriched uranium was needed for commercial nuclear power plants. The first process cell went online in September 1954. A gas centrifuge uranium enrichment program was initiated in the early 1980s at Portsmouth. However, full operation was never implemented for the centrifuge process.
The cleaning and change out of process equipment at the site generated spent solvents and other contaminants that were disposed of in on site landfills and surface impoundments. Contamination has also been found in process buildings, cooling towers, burial grounds and waste water ponds. Although the plant is now leased and operated by U. S. Enrichment Corporation, environmental restoration and related waste management activities associated with past practices will be conducted by the Department of Energy. However, under the provisions of the lease, future plant shut down and cleanup activities will be the responsibility of U.S. Enrichment Corporation.
| Federal Site Acreage | 3,708 acres |
| Gaseous Diffusion Plant Acreage | 640 acres (approximate) |
| Total Number of Buildings | 109 Buildings |
| Process Buildings | 3 |
| Process Buildings Dimensions | mile long, 550 feet wide, 80 feet high (approximate) |
| Process Building Acreage Under Roof | 93 acres |
| Number of Gaseous Diffusion Enrichment Stages | 2,100 stages (approximate) |
| Peak Design Power Capacity | 2,100 megawatts |
| Largest Process Motor | 3,300 horsepower |
| Water Utilization | 20 million gallons/day |
| Number of Control Instruments | 90,000 (approximate) |
| Miles of Copper Tubing | 1,000 |
| Miles of Process Tubing | 600 |
| Miles of Roadways | 30 |
| Miles of Railroads | 20 |
| Miles of Boundary Fence | 11 |
| Miles of Security Fence | 4 |
| Perimeter Road Circumference (miles) | 7 |
PHYSICAL FACILITIES
| Process Buildings | Laboratory | Sewage Plant |
| Cafeteria | Maintenance Shop | Warehouse Facilities |
| Fire Headquarters | Administration Buildings | Vehicle Maintenance |
| Security Headquarters | Steam Plant | Process Support |
| Medical Facility | Water Treatment Plant |
PORTSMOUTH GASEOUS DIFFUSION PLANT TIMELINE
| August 1952 | U.S. government selects Pike County site for new Portsmouth uranium enrichment plant. |
| September 1952 | U.S. officials select Goodyear Tire & Rubber Corporation as plant operator; and Goodyear creates Goodyear Atomic Corporation to operate plant. |
| September 1954 | First production cells go "onstream." |
| March 1956 | Contractors complete entire Portsmouth plant six months ahead of schedule and full production begins. |
| Mid-1960s | Plant shifts from military mission to commercial application to supply enriched uranium to electric utilities operating nuclear power plants. |
| January 1975 | NRC (Nuclear Regulatory Commission) and the Energy Research and Development Agency (ERDA) assume AEC functions. NRC takes over regulatory oversight of nuclear power plants and ERDA, which would later be absorbed by the U.S. Department of Energy (DOE), assumes responsibility for uranium enrichment. |
| October 1977 | Government transfers ERDA functions to newly created DOE. |
| November 1986 | Martin Marietta Energy Systems, Inc. takes over Goodyear's operating contract for plant. |
| November 1992 | Energy Policy Act creates USEC to take over government's uranium enrichment enterprise. |
| July 1993 | USEC assumes responsibility for Paducah, Kentucky, and Portsmouth, Ohio, uranium enrichment plants. DOE retains responsibility for environmental restoration and waste management activities resulting from its operations at site. |
| July 1993 | USEC contracts with Martin Marietta Utility Services, a newly created subsidiary of Martin Marietta, for operation and maintenance of enrichment plants. |
| June 1995 | Lockheed Martin Corporation forms after merger of Lockheed and Martin Marietta corporations. Lockheed Martin Utility Services, Inc. (LMUS) continues operation of USEC's Paducah plant. |
| June 1995 | First shipment to USEC of Russian low enriched uranium derived from highly enriched uranium taken from nuclear warheads arrives at Portsmouth plant as part of historic Megatons-to-Megawatts contract. |
| November 1995 | USEC revises and renews operating contract with LMUS from cost-plus to performance-based contract. |
| November 1996 | NRC grants certificates of compliance for USEC's two enrichment plants. |
| March 1997 | Regulatory oversight of enrichment plants officially transfers from DOE to NRC. |
| July 1998 | USEC is privatized; becomes USEC Inc, an investor-owned corporation. |
| May 1999 | USEC takes over direct operation of Portsmouth GDP. |
![]() Portsmouth OH |
![]() Portsmouth OH Gas Centrifuge Enrichment Plant |

















